5- 4″ & 18″ spool drop object protection (flexible concrete mattress)
Project: South Pars Phase 13, 23Pipelines
Client: IOEC Co.
Project Status : DONE

5- 4’&18″ line spool drop object protection (flxible concrete mattress)
Project: South Pars Phases 13,23 Pipelines
Client: IOEC Co.
Project Status : DONE


  • 1-Freespan Correction and Pipeline stabilization (Grout bag supply and grouting Operation)
    Project: South Pars Phase 16 Pipeline (in trench)
    Client: IOEC/ RAL Co.
    Project Status : DONE


  • 2- Spool Piece Protection Flexible Concrete Mattresses construction
    Project: FOROOZAN Field Pipelines Spool Piece Installation
    Client: PETROIRAN Development Co / SYNERGY Subsea Engineering LLC
    Project Status : DONE


  • 3- 4″ piggyback stabilization / protection (Grout bag design, supply and grouting Operation)
    Project: South Pars Phase 15, 16 Pipelines
    Client: IOEC /SGK Co.
    Project Status : DONE

  • 4- 32″ line spool support (Grout bag design, supply and grouting Operation)
    Project: South Pars Phase 19 Pipelines
    Client: IOEC /RAL Co.
    Project Status : DONE

  • 5- 4″ & 18″ spool drop object protection (flexible concrete mattress)
    Project: South Pars Phase 13, 23Pipelines
    Client: IOEC Co.
    Project Status : DONE

  • 6- 8″&12″ line spool drop object protection (flxible concrete mattress)
    Project: Abouzar Oil Field
    Client: IOEC Co.
    Project Status : DONE

  • 7- 32″ spool drop object protection (flexible concrete mattress)
    Project: South Pars Phase 11 Pipelines
    Client: IOEC Co.
    Project Status : DONE